As a part of Project Decarbonization, we were employed by Economech Services to install a number of new chiller units onto the roof, Level 40 on the ANZ Center in Auckland City.
This complex project involved four unique stages executed over 9 months, at times the whole MR-L team were involved and was a great showcase of the teams skills and experience.
The Kahu NZ helicopter team were a great addition to the process and made the 21st of March 2026, lift day, run as smooth as could be.
We don’t often use a helicopter in our line of work, but when we do, we love it.